How to: Schedule Master Data Synchronization
The master data, such as LS Forecast Batches, LS Forecast Items, and LS Forecast Locations, are the pre-requisite components for LS Forecast to calculate forecasts. They must be set up in LS Central and uploaded to LS Forecast before the forecast calculation can be performed.
To perform the upload action, you have the options to upload the data manually or schedule the synchronization process by using the Scheduler Job.
For scheduling the calculation of LS Forecast see How to: Schedule LS Forecast Calculation.
To schedule synchronization of master data
- Click the icon, enter Scheduler Job List and select the relevant link.
- Create a new scheduler job by clicking the New action, or select an existing job.
- In the General FastTab, define the Job ID and Description.
- Select or create a new Scheduler Job Type Code.
- In the Object Setup FastTab, select Codeunit in the Object Type field and assign the Object No. with 10012331 (LS Forecast Master Data Sync.).
- Go to the Schedule Details FastTab, define the date and time when you would like the job to be executed. This includes Time Units, Time Between Check, Next Check Date, and Next Check Time.
To view the LS Forecast Calculation Logs see How to: View LS Forecast Calculation Logs.
See Also